Overview of Microgrid Results

Microgrid Name Generation Bus Minimum 1 hr Load (kW) Average 1 hr Load (kW) Average Daytime 1 hr Load (kW) Maximum 1 hr Load (kW) Minimum 1 hr Critical Load (kW) Average 1 hr Critical Load (kW) Average Daytime 1 hr Critical Load (kW) Maximum 1 hr Critical Load (kW) Existing Fossil Generation (kW) New Fossil Generation (kW) Existing Solar (kW) New Solar (kW) Existing Battery Power (kW) Existing Battery Energy Storage (kWh) New Battery Power (kW) New Battery Energy Storage (kWh) Existing Wind (kW) New Wind (kW) Total Generation on Microgrid (kW) Renewable Generation (% of Annual kWh) Emissions (Yr 1 Tons CO2) Emissions Reduction (Yr 1 % CO2) Average Outage Survived (h) O+M Costs (Yr 1 $ before tax) CapEx ($) CapEx after Tax Incentives ($) Net Present Value ($)
mg0 634 789 1,493 1,913 2,713 60 178 248 306 0 110 440 1,223 79 307 100 64 0 0 1,953 17 5,431 13 77 32,748 2,429,646 1,495,772 492,265
mg1 675 789 1,493 1,913 2,713 211 403 498 713 0 411 0 2,852 0 0 290 655 0 0 3,554 29 4,637 29 604 61,910 5,824,016 3,691,514 730,573
mg2 646 789 1,493 1,913 2,713 25 139 216 385 0 96 0 1,538 0 0 203 443 0 0 1,837 16 5,511 16 634 30,161 3,164,638 1,996,972 622,029
Summary None 789 1,493 1,913 2,713 296 720 962 1,404 0 617 440 5,613 79 307 593 1,162 0 0 7,344 21 15,579 19 77 124,819 11,418,300 7,184,258 1,844,867

Report Generated

2024-07-30 13:28:12.075967

User Warnings

Pre-existing battery battery_634_existing will not be utilized to support loads in microgrid mg0.
Supporting critical loads across microgrids assumes an AMI metering system. If not currently installed, add budget for the creation of an AMI system.
Supporting critical loads across microgrids assumes the ability to remotely disconnect 3-phase loads.

Distribution Upgrades needed to create Microgrids

Microgrid Location Recommended Upgrade Component Count Cost Estimate ($)
mg0 mg0 Microgrid Design 1 100,000
mg0 mg0 Microgrid Controls 1 100,000
mg0 632633 SCADA disconnect switch 1 50,000
mg0 634a_data_center AMI disconnect meter(s) 1 300
mg0 634b_radar AMI disconnect meter(s) 1 300
mg0 634c_atc_tower AMI disconnect meter(s) 1 300
mg1 mg1 Microgrid Design 1 100,000
mg1 mg1 Microgrid Controls 1 100,000
mg1 671692 SCADA disconnect switch 1 50,000
mg1 675a_hospital 3-phase relay(s) 1 20,000
mg1 675b_residential1 3-phase relay(s) 1 20,000
mg1 675c_residential1 3-phase relay(s) 1 20,000
mg1 692_warehouse2 3-phase relay(s) 1 20,000
mg2 mg2 Microgrid Design 1 100,000
mg2 mg2 Microgrid Controls 1 100,000
mg2 632645 SCADA disconnect switch 1 50,000
mg2 645_hangar AMI disconnect meter(s) 1 300
mg2 646_office AMI disconnect meter(s) 1 300

Description